Case Study · EV Charging Backbone · Level 1
Level 1 EV Charging Backbone, Waterloo NSW
About the Building
Waterfall by Crown Group is a mixed-use strata development in Waterloo, NSW, with 331 apartments across four buildings and retail at ground level. The developer’s project information lists approximately 316 car spaces across three basement levels.
Project Overview
Future Charging Solutions retrofitted the Waterfall apartments for Level 1 EV charging. The project brought 15 A charging outlets to selected resident parking bays so drivers could plug in overnight where they already park.
Two dedicated EV distribution boards on Basement 2 form the backbone. The project also added energy metering and data cabling to connect the charging infrastructure to the Level 1 charging system.
Key Features
- Dedicated EV distribution. Two EV distribution boards on Basement 2 support different parts of the complex.
- Level 1 charging at resident bays. Dedicated circuits supply 15 A switched socket outlets for overnight charging.
- Energy metering and communications. FCS installed one energy meter and ran data wiring to two communications modules.
- Cable routes suited to the existing car park. The design used existing cable tray where available, with conduit where needed.
Challenges and Solutions
Reaching bays on different basement levels
The selected bays were spread across the car park. The two distribution boards were positioned on Basement 2 to serve different building blocks. Cabling was routed from the relevant board to each selected bay.
Fitting new circuits around existing services
Columns, pipework and existing building services constrained the cable routes and outlet positions. The layout used existing cable trays where practical and placed outlets near the bays they serve.
Connecting the charging system to the building’s network
The EV boards needed a data connection as well as power. The design routed Ethernet from the existing communications room, and FCS ran data wiring to both communications modules.
Project Outcome
Residents in the selected bays gained access to overnight EV charging. The building now has dedicated electrical and communications infrastructure that can support additional connections as demand grows, subject to available capacity.
Key Results
- 10 dedicated 15 A Level 1 outlets in the revised installation scope
- 2 EV distribution boards installed on Basement 2
- 1 energy meter installed and data wiring run to 2 communications modules